There's no question that it's been a real challenge.
I spoke about the new terminal we're hoping to build. We've been in the environmental review process for nine years. Even if we get approval this year, we'll require several more permits, and then it's a six-year construction period. That's a long period from beginning to end. There's no question of that. We certainly believe that a faster, more efficient process would be in everybody's best interest.
We have the power to approve certain projects within the port ourselves. Our terminals and other partners sometimes feel we take too long to approve them, but for us to take two years is pretty rare.