Mr. Chair, Mr. Howden did give an estimate, assuming the safety case is well done. We have not received the safety case, but assuming the safety case is complete we are looking at a matter of three days as Mr. Howden said. The commission would take a day, so that is four days.
How long it would take after the decision is rendered to get the reactor back up is the role of AECL. That is not the role of the commission. I will turn that over to AECL.