Mr. Speaker, with regard to the Canadian surface combatant project, since July 1, 2016, the Canadian surface combatant project is following a "design then build" approach.
The prime contractor for the Canadian surface combatant project is Irving Shipbuilding Incorporated of Halifax, Nova Scotia.
In its capacity as prime contractor, Irving Shipbuilding released the request for proposals, RFP, on October 27, 2016, to 12 successfully pre-qualified bidders. The objective of the RFP is to select an existing warship design and design team to be under subcontract to Irving Shipbuilding for the purpose of modifying the design to meet Canada's requirements and to incorporate Canadian systems and equipment. On October 19, 2018, the government and Irving Shipbuilding announced Lockheed Martin Canada Inc. as the preferred bidder for the Canadian surface combatant design. This decision was entirely based on its demonstration of compliance with the mandatory requirements and on the final scores of each bid according to the pre-established evaluation criteria.
With regard to part (a), a total of 88 amendments were issued by Irving Shipbuilding between November 1, 2016, and August 13, 2018. These amendments were developed and issued to address enquiries from the 12 pre-qualified bidders, and to incorporate process improvements to the competitive RFP so as to maximize the opportunities for bidders to demonstrate the value of their solutions to Canada.
With regard to part (b), the Government of Canada spent a total of $11.8 million on the project’s legal fees during the period of time that the RFP was being amended. The detailed information to allow a further breakdown on the amount that was spent on only the amendments is not available.
Because Irving Shipbuilding released the RFP, it would also have incurred legal fees.
With regard to part (c), only one RFP was released, with firms submitting their bids in two parts. Submissions for the technical and value proposition portions closed on November 30, 2017, and submissions for the financial portion closed on July 20, 2018.
Three companies submitted bids in response to the RFP.
With regard to part (d), as noted in the response to part (c) above, only one RFP was released; three firms submitted bids.
With regard to parts (e) and (f), as noted above, only one RFP was released. None of the three bidders would qualify as a small business.