moved:
That Bill C-39, in Clause 128, be amended by
(a) adding after line 15 on page 90 the following:
182.1 (1) The Commission must determine whether an application for a certificate in respect of a pipeline referred to in subsection 182(1) is complete within 60 days after receiving it.
(2) If the Commission does not consider that the application is complete, it must notify the company to that effect and indicate what information is missing.
(b) adding after line 4 on page 93 the following:
185.1 (1) The Commission must determine whether an application for a certificate in respect of a pipeline referred to in subsection 185(1) is complete within 60 days after receiving it
(2) If the Commission does not consider that the application is complete, it must notify the company to that effect and indicate what information is missing.