I hope someone is nodding in the back.
For the La Promenade building, you know that a number of parliamentarians are in that building. I feel that we did very well there. That was delivered on time, and—if I remember well—it was below budget, or on budget. I'll just stick with that, that's good enough. So that was a big focal point.
You see what we're doing now with the Wellington Building. It's the same principle, renovations. These are older buildings. You have heard about the John A. Macdonald building—the former Bank of Montreal—which will now become Room 200, which you used to be familiar with in the context of the West Block. The West Block is the big chunk. It's now empty, we're working on it, and it's going well.
We are funded—$500 million plus—for doing these initiatives. This year as well, we've undertaken a body of work with respect to the East Block, which will be our next priority. Obviously, a lot of this work implies movement and staggering of actions, which kind of makes sense. Remember, when we started to work on the West Block, we started to do the tower for stabilization, then we emptied the West Block, then we were inside the West Block, etc. That's the way we operate.
Colleagues and members of the committee, you have probably heard the story about the kitchen that had to be relocated. The kitchen in the West Block had to be relocated, and we've done that. If I remember, we were below budget by about 10%, and we were on time. So we were $5.5 million under budget against a project that was quite substantial in nature. The food facility was budgeted for $33 million, and we executed it for $28 million. The Wellington building is budgeted at $23 million, so we're moving ahead with that.
La Promenade, which I mentioned, was on time and on budget at $81.5 million. This room here, this building, which used to be the photography gallery, has also been renovated. We saw this as an opportunity to have more committee rooms, which were not sufficient in La Promenade building. This was done on budget and on time. I would say that we have a rhythm at LTVP in general right now. We've refined our planning, and we've been delivering these projects—and again I repeat myself—on budget and on time.
There will be surprises because these are older buildings. Mr. Chairman, you're very familiar with this. I remember walking through the West Block with the previous chair and some members of the committee when stones were being removed to allow stabilization for seismic work. They were surprised to see that these stones were numbered, cleaned up, and then put back in order after the stabilization work. So it is tedious work, which is expensive, but as the OAG noted in her report, it's probably worthwhile and expected by Canadians.