As I said, the project is doing well right now. In terms of the excavation and in terms of the parliamentary welcome centre, that is really progressing well. In terms of the schematic design, it's also completed. We're now moving on to design development.
I'm going to say that, in terms of progress, the involvement of the working group established by the board is very helpful to receive feedback on decisions from the point of view of members and their needs. As we've often said, this is your workplace. We want to do a modern Parliament that will serve your needs. That engagement is key to the success of this project.
In terms of decisions that have been made or recommendations that have been made by the working group and recommended to the board, an example is the infill of the Hall of Honour, where there will be three additional floors for the benefit of members.