Evidence of meeting #53 for Natural Resources in the 45th Parliament, 1st session. (The original version is on Parliament’s site, as are the minutes.) The winning word was waste.

A recording is available from Parliament.

On the agenda

Members speaking

Before the committee

Clavero  Chief Executive Officer, Conexus Nuclear Inc.
Godbout  Director of the Department of Engineering Physics, Polytechnique Montréal
J. McPherson  Director of Innovation, Centre for Nuclear Energy Research, University of New Brunswick
Hall  SLOWPOKE-2 Reactor Manager, Polytechnique Montréal
Dalzell  Vice-President, Corporate Affairs and Market Development, Bruce Power
Wilson  President and Chief Executive Officer, Nuclear Waste Management Organization
Vera-Perez  President and Chief Executive Officer, Organization of Canadian Nuclear Industries

The Chair Liberal Terry Duguid

Thank you.

Colleagues, let me thank our witnesses on your behalf. It was a great panel this morning, with a strong focus on research and development and workforce development.

I want to thank our analysts for putting together a complementary set of witnesses for us, as they try to do in all of our studies.

With that, colleagues, we are going to suspend for about five minutes while we change over to the next panel.

The Chair Liberal Terry Duguid

Colleagues, we're back in session.

As you know, bells are likely to go off a little after 12:30. We will be able to hear our witnesses and then likely, with the will of the committee, have about 15 minutes or so of Qs and As. I think we'll have time for one round, maybe even a reduced one round. We will see where we're at.

Welcome to our witnesses. We have with us, from Bruce Power, Pat Dalzell, vice-president, corporate affairs and market development. From Nuclear Waste Management Organization, we have Derek Wilson, president and chief executive officer, and Dakota Kochie, director, government and external affairs. From the Organization of Canadian Nuclear Industries, we have Ivette Vera-Perez.

Dakota, I think you're from Manitoba. We go back a ways, don't we? I will talk to you later.

Welcome to all.

Our virtual witnesses have conducted the mandatory witness onboarding test, and I have a few comments for the benefit of the new witnesses.

Please wait until I recognize you by name before speaking. Also, as a reminder, all comments should be addressed through the chair. Each of you will have five minutes for your opening remarks, after which we will open the floor to questions.

Mr. Dalzell, we're going to start with you for five minutes.

Pat Dalzell Vice-President, Corporate Affairs and Market Development, Bruce Power

Thank you, Mr. Chair and members of the committee, for the opportunity to appear today as part of the study of Canada's nuclear future. As you said, my name is Pat Dalzell. I'm the vice-president of corporate affairs and market development at Bruce Power.

By way of background, Bruce Power operates one of the world's largest nuclear generating facilities and provides about 30% of Ontario's electricity. We're currently advancing one of Canada's largest clean energy infrastructure programs through our life-extension program. Our experience gives us a practical perspective on what it takes to deliver large-scale nuclear projects safely, affordably and successfully.

I'd like to leave the committee with a simple message: Canada does not need to start from scratch to build its nuclear future. We'll build on the expertise, infrastructure, workforce and project delivery experience we already have.

The discussion today is no longer about whether nuclear energy has a role to play but what the next steps are in making that future a reality. As electricity demand continues to grow, driven by electrification, economic growth, data centres and energy security considerations, the question is, increasingly, how Canada will best deliver new nuclear capacity efficiently, affordably and on schedule. Our experience at Bruce Power demonstrates that we can.

Through our refurbishment program, we have shown that large and complex nuclear projects can be delivered safely, on schedule and with strong cost discipline. Most recently, our unit three major component replacement project was completed ahead of schedule and on budget. In fact, we returned unit three in early June, seven months ahead of schedule, just in time for the high-demand days of summer in Ontario, and it's been providing that electricity 24 hours a day, seven days a week, ever since.

In our view, experience matters. Established sites, experienced workers, mature supply chains and strong project governance are critical ingredients for successful project delivery. Those are advantages Canada already possesses and should continue to build upon.

The second point I'd like to emphasize is the importance of regulatory efficiency. Canada has one of the most respected nuclear regulatory systems in the world, and maintaining that standard is non-negotiable. However, we believe there are opportunities to improve efficiency and predictability by reducing duplication between federal assessment processes and the expertise-based review conducted by the Canadian Nuclear Safety Commission. The issue is not safety; the issue is duplication. We can maintain world-class environmental protections, indigenous engagement and nuclear oversight while creating more efficient and predictable approval processes.

My third point is that investment certainty matters. Nuclear projects require significant upfront investment, but they provide reliable, emissions-free electricity for generations. Federal investment tools, including investment tax credits and financing mechanisms, can help attract private capital, improve project certainty and support long-term infrastructure development that supports our Canadian economy while maintaining affordability.

A Canadian Manufacturers and Exporters report that's being released this week finds that the four nuclear projects planned in Ontario will contribute $882 billion in GDP and 3.45 million job-years across Canada. It's estimated that these projects will require up to one million tonnes of Canadian steel. These are significant impacts to our economy and, importantly, at Bruce Power the benefits of the clean electricity investment tax credit, in particular, flow directly through to Ontario ratepayers through the lower investment costs reflected in our price of power. The return on federal support is simple: lower costs, more investment, good jobs and reliable Canadian energy for decades to come.

Finally, Canada has a significant competitive advantage in its nuclear workforce and supply chain. The long-term investments made in the refurbishment program have helped create the highly skilled workforce and strengthened domestic manufacturing capacity that must be leveraged to power our future. Canada has the talent, expertise and the industrial capability needed to succeed. The key is providing the long-term certainty necessary to grow that advantage and to deliver the next generation of nuclear projects.

Mr. Chair, Bruce Power's experience demonstrates that Canada has the expertise and the industrial foundation to achieve its nuclear ambition. The priority now is ensuring that the federal policies, regulatory processes and investment frameworks enable that capability to be deployed safely, competitively and efficiently.

Thank you, and I look forward to your questions.

The Chair Liberal Terry Duguid

Thank you, Mr. Dalzell.

We're going to go now to Mr. Wilson and Mr. Kochie.

You have the floor for five minutes.

Derek Wilson President and Chief Executive Officer, Nuclear Waste Management Organization

Thank you, Mr. Chair. I appreciate the invitation to be here.

I'd like to begin by acknowledging that the session we are participating in today is being conducted on the traditional and unceded territory of the Algonquin peoples.

I'm glad to be among industry and government colleagues who understand the importance of ensuring Canada's nuclear sector can continue to support our country well into the future. I'm proud to be the president and CEO of the Nuclear Waste Management Organization, an organization created by an act of Parliament in 2002 to develop and implement Canada's plan for the safe long-term management of used nuclear fuel.

We are an independent, not-for-profit organization, and we are fully funded by Canada's nuclear fuel waste producers. By funding us, the waste producers demonstrate responsibility for implementing a long-term management plan. As witnesses come forward to testify about developments across the sector and new technologies on the horizon, Canadians and indigenous peoples can rest assured that the safe and secure management of radioactive waste is never an afterthought.

While utilities take accountability and continue to safely manage waste streams at reactor facilities, the current approach is interim, and a permanent long-term solution is required. It is internationally recognized that deep geologic repositories, or DGRs, represent the best way to protect people and the environment over the long term.

Earlier this year, the federal government released its nuclear energy strategy for Canada, which recognized the importance of world-class, long-term nuclear waste management. This strategy confirms that Canada is among the leading countries in the world, on a clear path to closing the nuclear fuel cycle while keeping people and the environment safe.

One of our organization's core values is that we owe it to future generations to not leave the waste that we created and benefited from as a burden for them to manage. That is why we're implementing a solution in this generation. In November 2024, we delivered on that promise by selecting Wabigoon Lake Ojibway Nation and the Township of Ignace as the site for the project. The people of both communities demonstrated their willingness to move forward by conducting their own community processes. This historic decision for Canada was driven by their thoughtful leadership, over a decade of active engagement to learn more about the project and time spent considering the future of the communities they call home.

Construction of the DGR will begin only after regulatory approval. We are actively building the evidence, designs and relationships that regulators need to make a sound decision. Our commitment to scientific excellence will stay with us throughout the regulatory reviews and into the responsible, well-managed construction and operations of Canada's first DGR.

The NWMO is currently engaged in the Major Projects Office process to have Canada's DGR for used nuclear fuel considered for listing under the Building Canada Act. This process reinforces the importance of this project for Canada's long-term energy security and prosperity. We are committed to working closely with governments to ensure regulatory processes are more coordinated and more efficient while preserving safety and necessary oversight.

The successful implementation of the DGR for used nuclear fuel will allow for a solid foundation to implement projects supporting new technologies and their waste streams. Canada's net-zero future and energy security increasingly demand new nuclear, from refurbishments to small modular reactors, full-scale build-outs and other emerging technologies.

That growth is good news, but it also means we owe the country a plan for how we manage the new radioactive waste being created. Public support for new nuclear depends on safe, socially acceptable waste solutions.

Recognizing NWMO's expertise and success, in October 2023, the ministry of Natural Resources Canada tasked the NWMO with implementing a second deep geologic repository. The second DGR will be built to house both intermediate-level and high-level radioactive waste, including used fuel from future reactors. Planning for that second repository is still in the early stages of development, and a new siting process is moving towards launch in 2028. The second repository gives us the opportunity to plan for what's emerging and to build on what we've learned.

The next few years will be telling. Success looks like a project that moves from planning into execution, progress that Canadians and indigenous people can see and trust. We made a promise to not leave nuclear waste as a burden for future generations. We plan to keep it.

Thank you. Meegwetch.

The Chair Liberal Terry Duguid

Thank you for that.

Finally, we move to Ms. Vera-Perez.

You have the floor for five minutes.

Ivette Vera-Perez President and Chief Executive Officer, Organization of Canadian Nuclear Industries

Thank you, Mr. Chair and members of the committee, for inviting me to contribute to your study on Canada's nuclear future.

My name is Ivette Vera-Perez. I am the president and CEO of the Organization of Canadian Nuclear Industries, OCNI. We represent almost 300 nuclear suppliers that employ approximately 20,000 highly skilled Canadians. Roughly 75% of our members are small and medium-sized businesses located in over 80 communities across the country.

Our role, plainly stated, is to turn contacts into contracts. We connect suppliers, utilities, project developers and governments to help Canadian companies secure work on nuclear projects, both domestically and internationally.

The opportunities are growing significantly. In Ontario, Bruce Power is advancing its refurbishment program and exploring new builds at Bruce C. Ontario Power Generation is also constructing the G7's first commercial, grid-scale SMR, preparing for Pickering refurbishment and exploring new builds at Wesleyville, Lambton and Nanticoke.

Ontario's nuclear expansion is expected to contribute more than $800 billion to Canada's economy and create approximately 150,000 job opportunities over these projects' lifespans. To put this into perspective, Canada's entire nuclear sector currently supports approximately 89,000 jobs and contributes roughly $22 billion annually to our economy.

Beyond Ontario, Alberta, New Brunswick and Saskatchewan—the latter of which generated approximately $2.6 billion in economic activity in 2024, through uranium mining and milling activities—are at various stages of exploring the use of nuclear energy in their systems. Collectively, these initiatives will increase demand for Canadian manufacturing, specialized services and skilled workers. This is where OCNI's direct work with industry becomes particularly important. We are using our knowledge and connectivity to lead initiatives aimed at strengthening the domestic nuclear supply chain and ensuring it's ready to capitalize on these developments.

In September, OCNI received $1.88 million from the Government of Ontario for a three-phase initiative to map supply chain capabilities and identify strategies to strengthen them.

In Saskatchewan, we are partnering with SIMSA and the Southeast Tech Hub, with support from PrairiesCan, to help local businesses gain the knowledge, qualifications and connections needed to enter the nuclear supply chain. The great news is that these projects could provide a foundation for a national level assessment.

Our team is also working to connect Canadian companies with projects and partners abroad. Over the last decade, OCNI has facilitated more than 20 trade missions to countries such as Romania, Poland, Sweden, Norway, the U.K., Argentina, India, South Korea, Japan, China and France, to name a few, and signed MOUs with supplier associations in over seven countries. These efforts have connected Canadian suppliers with international buyers and partners, opening doors to export opportunities across refurbishment, new build and SMR programs.

Our work on international relationships also gives us the unique insight into emerging projects, global supply chain requirements and the capabilities that Canadian businesses need to compete abroad.

With that in mind, OCNI encourages the federal government to focus on three priorities. First, undertake a national nuclear supply chain assessment to identify existing capabilities, current and future workforce needs, and strategies to address bottlenecks. Second, strengthen Canada's international competitiveness through export financing, coordinated trade promotion and co-operation on technical certifications, regulatory requirements and workforce mobility. Third, provide targeted financial grants and tax incentives to help suppliers purchase specialized equipment, expand manufacturing and meet nuclear-grade certification requirements.

Canada's nuclear future has the potential to strengthen Canadian manufacturing, support skilled employment and deliver lasting economic benefits to communities throughout the country. Our organization stands ready to work with government and industry to position Canadian suppliers and workers to seize these opportunities, both at home and internationally.

Thank you, Mr. Chair. I look forward to your questions.

The Chair Liberal Terry Duguid

Thank you to all of our witnesses.

Colleagues, we're going to be interrupted by bells shortly. We'll just take it as it comes, but we'll likely have time for just the first round of questions.

I apologize to our witnesses. You won't get grilled as heavily as you might have been if we'd had the full range of questions today. We also welcome briefs and follow-ups, so please feel free to do that.

Ms. Anstey, we're going to start with you for six minutes.

12:30 p.m.

Conservative

Carol Anstey Conservative Long Range Mountains, NL

Thank you, Chair.

Thank you to the witnesses. I'd like to start with Mr. Kochie and Mr. Wilson.

You talked about how in 2023 the federal government tasked you with planning the second underground nuclear waste repository, because the current storage arrangements are temporary and unsuitable for the long term. You have a site picked, but we have the target of 2050 for the waste disposal infrastructure.

Can you speak to the main factors that contribute to this lengthy time frame?

12:30 p.m.

President and Chief Executive Officer, Nuclear Waste Management Organization

Derek Wilson

The second DGR project was actually an outcome of the integrated strategy for radioactive waste, which was undertaken from 2020 through to 2023. In the recommendation of that, the NWMO was tasked by Natural Resources Canada to undertake that study on behalf of Canadians, so we did the study in that time frame.

In that study, we were looking at the entire life cycle of waste and all waste streams within that. The three recommendations coming out of it were that low-level waste was to be in near-surface disposal facilities, with the waste owners responsible for it themselves. Intermediate-level and high-level waste would be in a deep geologic repository. We already had used fuel in a deep geologic repository through the existing Nuclear Fuel Waste Act. When going through that study, we looked at both co-location with the first DGR as well as the potential for a second DGR location, specifically for intermediate-level waste and high-level waste.

At that time, new nuclear projects were being announced. Our current DGR that we're licensing up at the Wabigoon Lake Ojibway Nation and Ignace site is specifically for the existing fleet of CANDU reactors and the projected 5.9 million fuel bundles that are going to be created from that. We're looking at the potential for a second DGR.

We started our siting process for the first DGR in 2010, and we are expecting to be in operation by 2043. Taking lessons from that, we're trying to reduce the time frame from selecting a new site to getting it operational. We also want to be very cognizant of not interrupting the first DGR project, because that is going to be fundamental for us to be able to address the current liability on the ground, as well as being able to leverage that workforce. As we transition from the first DGR project, if a second DGR is required, we could transition those resources into that project.

12:30 p.m.

Conservative

Carol Anstey Conservative Long Range Mountains, NL

Okay.

I think about transportation of this waste as well. Is that something that you've considered when doing this work?

12:30 p.m.

President and Chief Executive Officer, Nuclear Waste Management Organization

Derek Wilson

The transportation for intermediate-level and high-level waste is, currently, already being done between reactor sites and interim storage facilities. It's already licensed activity and already well established within the existing operators, so we're not looking at that as part of the NWMO's mandate.

12:30 p.m.

Conservative

Carol Anstey Conservative Long Range Mountains, NL

Okay. Thank you.

I'd like to cede the rest of my time to my colleague.

12:30 p.m.

Conservative

Jeremy Patzer Conservative Swift Current—Grasslands—Kindersley, SK

Thank you very much.

I'm going to go to Bruce Power.

The Alberta Court of Appeal ruled on October 9 that Ottawa's 2024 legislative modifications failed to fix the core constitutional flaws previously identified by the Supreme Court of Canada. You mentioned in your opening remarks issues with the Impact Assessment Act in regard to duplicity.

I'm just wondering if you have any specific suggestions for this government beyond just the duplicity bit. If you wanted to expand on that, it's great, but do you have any suggestions for this government to try to help them get the Impact Assessment Act to be constitutional and respect provincial jurisdiction?

The Chair Liberal Terry Duguid

I'm sorry. Before you answer, if you don't mind....

Colleagues, the bells have rung. I need your agreement to continue. What I suggested was that we would just do the first round of questions.

Some hon. members

Agreed.

The Chair Liberal Terry Duguid

You have my apologies, Mr. Patzer.

Please proceed.

12:35 p.m.

Vice-President, Corporate Affairs and Market Development, Bruce Power

Pat Dalzell

Sure.

My remarks were really focused on what.... Actually, we think the solution, as we've recommended it here, of having the life-cycle regulator oversee the whole process from start to finish, including the impact assessment, is the right way to avoid some of those challenges.

Without getting into the legality of the previous version of the legislation, I would say, to us, the CNSC as the life-cycle regulator, doing the oversight and the decisions around the impact assessment for nuclear sites, is the right way for this to be shaped. We've been pretty consistent in our view that their being the experts in the nuclear field ultimately helps streamline the whole process. Making sure that the folks who are most informed about our industry and what we do and who have the history of our impact on the site and understand what we report out on...it helps reduce some of those duplicative processes and makes the outcome the best for the people of Canada and for our industry.

12:35 p.m.

Conservative

Jeremy Patzer Conservative Swift Current—Grasslands—Kindersley, SK

Some of the delays that possibly could have come from the duplication, like you're saying, from the process taking longer, what kind of impact have they had on projects or potential future projects for Bruce Power? What is the potential that could be lost going forward if these changes are not made?

12:35 p.m.

Vice-President, Corporate Affairs and Market Development, Bruce Power

Pat Dalzell

Ultimately, I think these changes will result in a better outcome, a more streamlined outcome. At the same time, we had already agreed on a charter with the Impact Assessment Agency that helped shape the timelines of the outcome for the site. At the end of the day, what we're looking at is better, safer outcomes for everybody, better understood outcomes and certainly a process where you don't have to go through the education piece.

As I said, the CNSC are the experts in this space. They would understand the regulatory filings that we've been producing. We've been operating at our site here for decades, and we consistently file environmental reports with the CNSC. We assume that ultimately you'd end up with a fairer, safer process.

The Chair Liberal Terry Duguid

Thank you both.

Ms. McKelvie, you have six minutes.

Jennifer McKelvie Liberal Ajax, ON

Thank you, Mr. Chair.

Thank you for the opportunity to ask questions to a former employer. It's been eight long years—certainly, I think political years are longer than real lifetime years—since I left the NWMO. What strikes me is the considerable progress that has happened. When I left, a site had not been identified.

I'm really wondering if you could speak to the value of a willing and informed community. That is something that I know was taken very seriously. I'm wondering if you could demonstrate what that process has been for the informing of the community and also how willingness is demonstrated through a consent-based process.

12:35 p.m.

President and Chief Executive Officer, Nuclear Waste Management Organization

Derek Wilson

Thank you. It's been eight years, has it?

Willingness is a foundation for our decision-making. We were not going to select a site if we didn't have an informed and willing host community. That was one of the three overriding criteria we had in our site selection process. It took time. We started the process in 2010 and made the decision in 2024, which was longer than we had originally anticipated, but it was required in order for the communities to become informed.

Informing happened in a number of different ways, depending on the community and on the level of knowledge in each of those communities. Really, we wanted to ensure that there was a grassroots acceptance and understanding of the project and the potential impacts of that project, both beneficial impacts and potential other impacts associated with a multi-billion-dollar project in their community.

The communities themselves decided how they were going to come to a consensus or a decision in which the community was engaged. In the case of Ignace, it was through a community-driven process where they sought to get an understanding of the community's willingness to accept the project. Wabigoon Lake Ojibway Nation did its own process throughout its own community. It wasn't the same, and we weren't prescribing how they had to do it.

What it does do is bring a level of knowledge so that they are making an informed decision. That, in our minds, was critical and foundational for a consent-based process. We're going to be applying that same consent-based process to the second DGR project as well, incorporating the learnings that we had through implementing adaptive phase management and going through the process to locate the first DGR site.

Jennifer McKelvie Liberal Ajax, ON

In the summer, your project was referred to the Major Projects Office. I'm wondering if you could speak to what you would like to see, should your project be designated. I'd also like some clarity around your timelines. The reason is that often for projects that are listed, we say on the government side that it would be one year, one process for review, but that clock doesn't start until the submission of the application. I think we need to be clear that, should your project be listed, this is not happening in a year. There are still additional steps that are there.

Can you walk us through what is left in the regulatory process for you and how the Major Projects Office could be a benefit?

12:40 p.m.

President and Chief Executive Officer, Nuclear Waste Management Organization

Derek Wilson

I think the Major Projects Office, from our perspective, is bringing some certainty around the regulatory timelines, as well as around the potential for efficiencies in those processes. If we can get efficiencies between the federal processes and the provincial requirements, provincial permits and so on, we see that as being potentially a mechanism where the Major Projects Office can help coordinate and collaborate through some of those issues.

As far as the overall timelines, we don't expect that the timelines are going to change significantly. As you say, we have a body of work that we have to do in order to prepare impact statements, whether they be through the Impact Assessment Agency of Canada or through the CNSC. Then there's the due diligence that the regulators have to do. There's a consultation process, and we want to ensure that there has been adequate consultation on the project.

In our minds, it brings more of a certainty of time as opposed to an opportunity for fast-tracking time. That's what we're really hoping to see out of this—that coordination and collaboration between the regulatory agencies—so that we have that efficiency. It gives us that comfort that we're going to be on the schedule we have in front of us, which is already assumed to be optimistic, given the existing IAAC process.