I thought they were accurate at the time based on the information we had given.
Just for another piece of information, the first estimates for Public Works to take on the function they had been asked to take on was over $70 million. That was way beyond what we paid Morneau Sobeco. The first estimate from Public Works to take on the function of RCMP pensions was over $70 million. I don't believe we were over $20 million transition costs.
Public Works ongoing costs, I am led to believe, are higher than Morneau Sobeco's ongoing costs. So if and when they chose to move to Public Works, I would suggest the cost will be significantly higher. This is information I have received.