Let me just touch on a couple of items there.
First of all, the overall costs of the projects are currently under review with the CER as part of our ongoing rate process. It has access to all of the documentation associated with the costs and the cost increases over time in order to assess those as part of our toll.
With regard to the sole-sourcing, direct assignment of the contract to McKinsey, at the time.... Look, the company had a lot of cost and productivity initiatives under way right from the beginning of the project in order to manage the schedule and costs. When McKinsey was hired, it was mid-project; it was about halfway through or even a little bit more than halfway through the project. Just in the ongoing desire to continue to look for ways to continually improve both the schedule and the costs, it was decided that we needed to bring in somebody who had very unique and specialized skills to help us look for opportunities that weren't already under way.