Thank you.
We had a report from a railway worker, a conductor in North Vancouver, in fact, who had provided some material. Some of the issues he talked about related to B.C. Rail, and it's covered, Mr. Chudnovsky, in one of your reports as well. He said that B.C. Rail maintained a joint derailment prevention task force consisting of senior management, union reps, and government regulators, which met quarterly to discuss derailment prevention strategies and review derailment reports, and that CN cancelled this.
That concerned me, with the combination of the difference in terrain and basically applying what appears to be a GOI suited to water-grade railways, or to more or less level railways that follow the levels of the rivers, in B.C.
What concerned me as well was that when they had the spikes they did have, particularly in the west, they didn't seem to respond fast. They responded, but it looks, in my opinion, as though it wasn't fast enough and wasn't identified.
The phase two audit reported that there were systems in place, and an adequate system, I think it said—I don't know whether the word “adequate” was used, but it implied that there was a good system in place—to report things. It's a question of the follow-up, between when the thing gets reported and the action is taken to respond to the problem.
I don't know whether Mr. Kosinski or Mr. Cotie have heard or would comment. I guess you're not able to talk about B.C. as such, but when we hear about these other derailments, such as in Ontario—yesterday, I think it was, and there have been other derailments as well—it doesn't appear to be only CN. CN seems to be the one we've heard most prominently about, and the audit, of course, was there.
The final question, Mr. Chudnovsky, is this. You mentioned that you had asked for four different packages of information and got one of them. It was frustrating for us, because under Mr. Lapierre, the federal Minister of Transport in the previous government, these audits were ordered and were going to be made public, and then they weren't. I gather that's for a combination of reasons—perhaps the Railway Safety Act, under which the approval of the railway is apparently needed to release some of this. It was very frustrating. I don't know whether you have any comment on that.