Mr. Speaker, with regard to government funding for the completion of the Arctic Bay small craft harbour since August 4, 2021, details are as follows. With regard to part (a)(i), the contract for design and inspection services is with Worley Canada Services Ltd. and Ikpiaryuk Services Ltd., in joint venture. The total amount of funding delivered to the joint venture since August 4, 2021, is $940,274.27.
With regard to part (a)(ii), there is no separate contract for Ikpiaryuk Services Ltd. as it is in a joint venture with Worley Canada Services Ltd., as listed above.
With regard to part (a)(iii), there are no other contracts on this project.
With regard to part (b), the original design and inspection contract has not been completed or cancelled.
With regard to part (c), the contract with Worley Canada Services Ltd. and Ikpiaryuk Services Ltd, in joint venture, has been amended four times since August 4, 2021. The details are as follows.
Amendment six, on a supplemental archaeological assessment, occurred on December 30, 2021. The Government of Nunavut culture and heritage branch has requested a supplemental archaeological impact assessment, AIA. The original AIA was completed as part of a prior Fisheries and Oceans Canada, DFO, feasibility study. The project areas have expanded to include a larger quarry footprint. Additionally, there are areas that the contractor may propose to utilize that have not yet been captured in the historical AIA. This amendment will capture the expanded areas and will require that the archaeologist coordinate their review with the contractor to ensure that all areas will be assessed.
Amendment seven, on a revised class A estimate and community consultation support, occurred on June 28, 2022. The costs incurred related to preparing a revised class A estimate, risk assessment and recommended contingencies. The original construction solicitation has been cancelled as prices were excessively high in relation to the original estimate. The class A risk and contingency assessment would support DFO in acquiring additional funding.
Amendment eight, on an increase to honoraria disbursement allowance, occurred on June 28, 2022. The increase to the disbursement upset limit related to any additional honoraria payments that may be required. Honoraria payments will be issued per the original terms of payment contained in amendment 001.
Amendment nine, on the translation of drawings and specifications, occurred on September 6, 2022. Advisian-Ikpiaryuk has submitted a proposal to provide translation of the issued-for-tender drawings and specifications in order to meet the obligations of policy notification PN48R1.
With regard to part (d), since August 4, 2021, DFO has engaged with the community of Arctic Bay on three occasions.
On September 14, 2021, DFO held a community open house to review and present the final harbour design and discuss construction methodologies, haul routes and quarry works. The community open house attendees included community residents and representatives from the hamlet of Arctic Bay; the Ikajutit Hunters and Trappers Association; the Arctic Bay Nauttiqsuqtiit, or the guardians; the Qikiqtani Inuit Association; DFO; Transport Canada, TC; Public Services and Procurement Canada, PSPC; and consultant representatives from Worley Canada Services Ltd. and Ikpiaryuk Services Ltd, in joint venture.
On September 15, 2021, DFO held a meeting at the community hall to review the findings and information gathered at the public open house and to formally consult on any potential impacts to fish and fish habitat caused by the project as well as on navigation requirements and disposal-at-sea requirements. Meeting attendees included representatives from the hamlet of Arctic Bay; the Ikajutit Hunters and Trappers Association; the Arctic Bay Nauttiqsuqtiit, or the guardians; the Qikiqtani Inuit Association; DFO; TC; PSPC; and consultant representatives from Worley Canada Services Ltd. and Ikpiaryuk Services Ltd., in joint venture. Environment and Climate Change Canada representatives attended the meeting remotely.
On December 1, 2021,DFO held a final meeting prior to going to tender at the community hall in Arctic Bay. Worley Canada Services Ltd. And Ikpiaryuk Services Ltd., in joint venture, provided a presentation, followed by open discussion to review the final harbour design, construction methodologies, haul routes, navigation aspects, impacts to fish and fish habitat, and quarry works. Community feedback from the open house was reviewed and presented. Meeting attendees included representatives from the hamlet of Arctic Bay; the Ikajutit Hunters and Trappers Association; the Arctic Bay Nauttiqsuqtiit, or the guardians; the Qikiqtani Inuit Association; and Worley Canada Services Ltd. and Ikpiaryuk Services Ltd., in joint venture. DFO and PSPC participated remotely due to winter storms preventing travel to the community.
With regard to part (e), at this time, the completion date is unknown.