Thank you, Mr. Chair and members of the committee, for the invitation to be here.
I'm Tara Shea, vice-president of regulatory and indigenous affairs with the Mining Association of Canada. I'm joined by my colleague Geoff Smith, our vice-president of government relations.
I want to begin by recognizing that we are gathered today on the traditional territory of the Algonquin Anishinabe people.
Mining is a cornerstone of Canada's economy, and global demand for Canadian minerals and metals continues to grow. To meet this demand, we need timely permitting approvals for new mines and existing operations.
We also need reliable rail, port and marine networks that are protected from prolonged work stoppages. The Canadian mining sector is the largest industrial customer of Canada's railways and the largest shipper by volume in both rail and marine.
Our sector has a stake in all three parts of Bill C-39.
MAC views Bill C-39 as another step in the right direction. The changes to the Fisheries Act to enable third party habitat banking and fee-in-lieu alternatives, as well as the reforms under the Canadian Navigable Waters Act, are particularly welcome, but legislation alone will not deliver the efficiency Canada needs. Implementation is critical.
We have provided the committee with a detailed brief, and we'll use our time today to highlight a few of our key recommendations.
Starting with the Impact Assessment Act, we acknowledge the agency's ongoing work to focus assessments on issues within federal jurisdiction. Even so, a federal impact assessment remains a substantial undertaking, and there's opportunity for further improvements. Shorter timelines are achievable. Realizing them in practice will require pairing the timeline reforms with a recalibrated scope of study and information requirements, so that what proponents must produce matches what decision-makers actually need. Without this, we are compressing timelines on paper, not in practice.
Next, most provinces have now signed impact assessment co-operation agreements. We would like to see clearer recognition of these agreements in the legislation itself. We recommend amending section 16 of the Impact Assessment Act to screen out projects where an agreement is in place and where the province confirms that its processes, together with federal permitting, will address effects within federal jurisdiction. Where a federal assessment is nonetheless required, the agency should publish its reasons for requiring a federal assessment.
Finally on the Impact Assessment Act, the physical activities regulations—the project list—should be amended to focus on projects that have the potential for significant adverse effects within federal jurisdiction. For mining, that means, at a minimum, excluding mine and mill expansions, raising production thresholds for new mines and mills, and excluding small-footprint projects like electrified underground mines.
Moving to part 2 of Bill C-39, we support the government's ambition to improve supply chain efficiency, the new transportation projects office, the national trade corridors councils, the tell-us-once approach under the Canada Transportation Act and more flexibility for ports. Their effectiveness will depend on implementation, including a clear scope for new powers and adequate federal resources.
Beyond Bill C-39, Canada needs a broader review of the Canada Transportation Act to address the market power of the two class I railways.
Finally, on labour, Bill C-39 includes important amendments to the Canada Labour Code. However, under the proposed framework, the minister can intervene only once the strike or lockout has begun. By then, mines have likely already cut production and, potentially, jobs. These disruptions also damage customer relationships and Canada's reputation with trading partners and investors. We recommend amending section 107 of the Canada Labour Code to allow intervention before a stoppage in exceptional circumstances only: where bargaining has failed, where the special mediator says a stoppage is imminent and where the harm to the national interest would be significant.
In closing, investors look at the whole picture, including how long it takes to get a project approved and whether they can reliably get their product to market once it's built. To attract the investment, we need assessment and permitting information requirements to be scoped to what is actually needed to make decisions; processes that deliver on legislated timelines; early, coordinated and meaningful indigenous consultation; and sustained federal, provincial and territorial co-operation. We also need a resilient transportation system with the tools to prevent costly disruptions before they start.
Thank you. We'll be happy to answer your questions.